
Tokyo Electric Power Co. (TEPCO) gives a lecture to the media regarding
No. 3 reactor at TEPCO's Kashiwazaki-Kariwa nuclear power plant in
Kashiwazaki, Japan, July 28, 2007. The world's biggest nuclear plant
performed safely during and after an earthquake in Japan but it may take
more than a year to restart power production, U.N. inspectors said on
Friday.

The world's biggest nuclear plant
performed safely during and after an earthquake in Japan but it may take
more than a year to restart power production, U.N. inspectors said on
Friday.
"It will take at least months, maybe a year or more. I would be
surprised if it was less than a year," said Philippe Jamet, a senior
International Atomic Energy Agency official.
Janet, who headed an IAEA team that examined the plant, said in-depth
inspections of the Kashiwazaki-Kariwa reactor vessel and fuel elements
had yet to be done.
If damage was discovered there, bringing the plant back on line could
take even longer, he said.
The plant leaked low amounts of radiation -- below the maximum permitted
under safety rules -- when a 6.8 magnitude quake struck on July 16,
exceeding the worst seismic impact that the plant had been designed to
withstand, according to a 39-page report issued at IAEA headquarters in
Vienna.
"The installation behaved in a safe manner during and after the
earthquake. In particular, the automatic shutdown performed
successfully," the report said.
The plant will remain closed indefinitely for safety checks and the
Japanese government has ordered other nuclear plant operators to
undertake strict safety checks.
While safety-related systems and components of the plant, run by Tokyo
Electric Power Co. (TEPCO), seemed to be in surprisingly good condition,
other key components had yet to be checked thoroughly, Jamet said.
"Another consideration is the possibility that long-term operation of
components could be affected by hidden damage from this event," the
report by his six-strong team said.
LONGER-TERM WEAKNESS?
Such components, in effect, could function well under normal conditions
but not necessarily during a future accident, or safely over the longer
term.
Non-safety related systems and components sustained serious damage from
factors such as soil deformation and oil leakages, said the report.
"A re-evaluation of the seismic safety the Kashiwazika Kariwa nuclear
power plant needs to be done with account taken of the lessons learned
from the... earthquake and using updated criteria and methods."
Jamet said radioactive releases into the air and sea from the stricken
plant were "extremely small" and the health and environmental impact was
"practically negligible."
He also praised the cooperation and transparency of Japanese officials
dealing with his mission on August 6-10.
Japan's nuclear industry has been tarnished by cover-ups of accidents
and fudged safety records. About one third of Japan's electricity grid
is supplied by nuclear power, which has been central in Japanese efforts
to combat global warming.
Japan initially told the IAEA it did not need help after the quake.
Later, it said it would allow inspectors into the plant after local
authorities expressed concern that talk of the plant's problems would
damage tourism and fisheries.
|